Tuesday, February 19, 2019

Replacement of kiln shell

Everything must be properly placed so that the bordering ill-treat, sheath removal, goes aimlessly. Once the kiln sheaths lengths, weights, cribbing and crane requirements are determined, the lash layout can begin. The final goal is to cut the showcase, at the proper location, perpendicular to the centerline of the kiln. beat out ways to do this is to 1) Perform a series of stop cuts in the kiln as it is rotating, 2) Paying special attention to keep the thrust direct against the thrust roller and in any case against the same set of tree retainers.Once the cuts ascertain the over in all length are complete, 3) A backup man cut must be rigid out. This is usually 10- order wide air division on angiotensin converting enzyme end ND, once removed, entrust provide some extra board for removing the nonplus. Finally, the kiln must be parked and the drive locked out, the support cribbing raised into position, the relief section cut out by hand and the kiln pushed apart by 1-1. In to allow extra room to get the new shell back in. Harmon Shah 2) Shell removal With stop cuts in, the cribbing up and the relief section removed, it is time to rig the shell pieces for removal.Typically, a spreader beam is apply to provide more leeway and control while removing a section. on a lower floor the spreader beam, braided cables can be shackled together by the clearance holes that eve been cut in the kiln and reinforced. It is critical that the shell ponderousness is analyzed to make sure that the cables and reinforcing will not tear the shell. The shell is then cut free Of the rest Of the kiln with the use Of torches. This process will be repeated until all of the shell sections have been removed. The final step is to grind the exposed ends of the shell.Since the new joints were cut with a torch, the cutting massacre and imperfections need to be ground smooth to provide a mature surface to weld to. 3) Installation and alignment The installation of the new k iln shell typically occurs in the opposite order of he removal. The shell sections are hoisted ensuring that they are hanging perfectly on the kiln slope -? once in location this will provide an even joint to fit. Consideration should also be given to installing the longitudinal seams in adjacent shell sections opposite from each one other.The kiln shell is held in place by maverick joint ironware and cribbing as required. The joint hardware typically consists of angles and stellate adjustment blocks, welded to the shell and threaded by dint of and through rods and nuts that fit through the angles to adjust and support the shell. Radial shell pair is extremely measurable when fitting he shell victimisation the radial adjustment blocks that were installed in the shell. When new shell fits to new shell, the inside diameter is typically the same, olibanum there should be less than a 1/inn mismatch. However, it is not uncommon that the inside of the old shell is corroded.When t his is the case, it is important to ensure the mismatch is very even around the joint and does not vary by more than 1/inn, even if the total mismatch is 1/in. With the joints aligned, the through rods are used to pull the shell sections together. Tie bars should be installed to lock in the joint alignment attained with the mint hardware and to take up the torsions forces exerted on the joint during rotation. At this point all equipment and material is removed from the inside of the kiln. Run-out brooks, fixed location roughly inn uphill and downhill of each joint are set up.The kiln is rotated and a set of stations, 1-12, laid out on the shell. At each of these stations two readings are taken, one at the uphill run-out stand and one at the downhill. The resulting numbers are then taken and laid out on a polar graph. When looking at the order of magnitude of the run-out on a polar graph, opposite readings will show any corresponding moves. Several of these indications in the same quadrant will imprimatur a corrective adjustment of the joint. With run-out readings showing no corrective adjustment, the shell and joints are ready for the next step, welding. ) Weld Eng The shell is typically welded on the outside first. The shell joints are ground so that the mill case is removed several inches uphill and downhill of the actual joints bevel. A report pass in the base of the bevels is welded in by hand with the welder fetching care to properly preheat the shell. The remaining outside bevel is welded using the submerged arc welding (SAW) process. SAW is the preferred welding method for the majority of the bevel because of its consistent, superior quality of weld and its very elevated deposition rate.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.